Multi-let office buildings in Leeds: EVC charger installation

Electric Vehicle Charger installation at two multi-let office buildings in Leeds as part of a new lease agreement

Find out more

Installation

  • Chargers: 6 x 7kw Alfen 1PH 2FC dual chargers serving 12 parking bays (6 bays in each car park). 
  • Assure Care Plan: Annual service, maintenance and guaranteed 98% operational uptime.
  • Management Software: Annual remote management and 3G data, advanced access control, flexible pricing and power management.
  • 24/7/365 quality, dedicated ChargePoint connected Driver Support.

Opportunity

Our client was instructed to install Electric Vehicle Chargers (EVCs) across the car parks of two multi-let office buildings in Leeds as part of a new lease agreement.

Solution

By using the existing landlord electricity supply run from the substation in the bottom of the car park, we were able to supply both car parks with chargers by installing them on either side of the car park boundary. This reduced the disruption by undertaking both projects at one time and kept costs to a minimum through a reduced cable run and groundworks.